The original Seven Essays, in a cool, new outfit ...
Email - [email protected]

All posts in General Questions

Need help answering the questions noted below. If you use the work of others in answering the question, please cite using correct APA style.

Categories: General Questions
Comments Off on Need help answering the questions noted below. If you use the work of others in answering the question, please cite using correct APA style.

Need help answering the questions noted below. If you use the work of others in answering the question, please cite using correct APA style.

What are the purposes of scholarly writing? How do the components of scholarly writing help achieve those purposes?

1. What required experience is needed when assessing safety/security programs, operations, processes, equipment and systems?

Categories: General Questions
Comments Off on 1. What required experience is needed when assessing safety/security programs, operations, processes, equipment and systems?

1. What required experience is needed when assessing safety/security programs, operations, processes, equipment and systems?

2. If there were critical safety/security challenges confronting a zoo environment; what steps would a manager take to overcome them?

3. What are possible goals to achieve within the first six months as a zoo safety/security manager? Why?

4. Issues will arise in developing, reviewing, recommending and monitoring zoo safety/security policies and procedures; what could be the major issues in a zoo environment and how could some of these issues be addressed?

5. Describe significant written document/report/presentation, which has to be completed in zoo safety/security management.

2. A sales project at month 5 had an actual cost of $34,000, a planned cost of $42,000, and a value completed of $39,000. Find the cost and schedule variance and the CPI and SPI.

Categories: General Questions
Comments Off on 2. A sales project at month 5 had an actual cost of $34,000, a planned cost of $42,000, and a value completed of $39,000. Find the cost and schedule variance and the CPI and SPI.

2. A sales project at month 5 had an actual cost of $34,000, a planned cost of $42,000, and a value completed of $39,000. Find the cost and schedule variance and the CPI and SPI.

4. A project to develop a county park has an actual cost in month 17 of $350,000, a planned cost of $475,000, and a value completed of $300,000. Find the cost and schedule variances and the three indexes.

6. A project to develop technology training seminars is 5 days behind schedule at day 65. It had a planned cost of $735,000 for this point in time, but the actual cost is only $550,000. Estimate the schedule and cost variances. Re-estimate the variances if the actual cost had been $750,000.

8. For the following test marketing project at week 6, calculate the cost, schedule, and time variances. Also, calculate the CPI, SPI, CSI,, and the ETC and EAC.

Activity Predecessors Duration WKs Budget $ Act Cost$ % completed
a — 2 300 400 100
b — 3 200 180 100
c a 2 250 300 100
d a 5 600 400 20
e b,c 4 400 200 20

10. Resolve problem 8 using MSP. Omit the calculations for CPI, SPI, and CSI.